​Ho Chi Minh City’s first metro tunnel nears completion 

​Ho Chi Minh City’s first metro tunnel nears completion 

Thursday, October 19, 2017, 16:00 GMT+7
​Ho Chi Minh City’s first metro tunnel nears completion 
A section of the tunnel from Ba Son Station to the Municipal Theater in District 1, Ho Chi Minh City. Photo: Tuoi Tre

As of Wednesday, 775 meters of the 781-meter long underground passage had been completed.

The tunnel runs from Ba Son Station to the Municipal Theater in District 1, part of the city’s metro route No.1 connecting Ben Thanh Terminal in District 1 with Suoi Tien Terminal in District 9.

The installation of the boring machine was started in March and tunnel construction began in May.

The Japanese-made tunnel boring machine (TBM) is about to finished drilling a 781 meter long metro tunnel in Ho Chi minh City.
The Japanese-made tunnel boring machine (TBM) is about to finish drilling a 781-meter long metro tunnel in Ho Chi Minh City.

According to a representative of Japan’s Shimizu-Meada Joint Operation, the main contractor for the tunnel project, over 40 engineers and workers have been working around the clock to finish the job.

The underground passage is expected to be finished on October 31, two months ahead of schedule, he stated.

Following the completion, the TBM, a 70-meter long machine weighing 300 metric tons, will be disassembled.

About 775 meters of the 781 meter long underground passage have been completed.
About 775 meters of the 781-meter long underground passage has been completed.

Its parts will be transported back to Ba Son Station to be re-assembled – a three month project – before construction of a second tunnel between Ba Son and the Municipal Theater begins.

This entire passageway is anticipated to be completed in mid-2018.

Engineers carry out the finals phases of the construction.
Engineers carry out the final phases of the construction.

The Japan International Cooperation Agency, a provider of capital assistance for the metro project, says this is the first time a TBM has been operated in Vietnam.

The technology used with the machine helps minimize vibrations and noise during the tunnel construction.

The entrance of the tunnel at Ba Son Station
The entrance of the tunnel at Ba Son Station

According to the Ho Chi Minh City Management Authorities for Urban Railways, the construction of metro route No.1 began in August 2012 with the total investment capital of US$2.49 billion.

Plans for the metro line call for 19.7 kilometers of track to pass from District 1 through District 2, District 9, Binh Thanh District, and Thu Duc District. 

The expected completion date is in 2020.

The railway has been installed on the the completed section of the tunnel.
The railway has been installed on the the completed section of the tunnel.
A worker operates the machine at a control center.
A worker operates the machine at a control center.
Ba Son Station is being constructed.
Ba Son Station is being constructed.
Material is transported into the tunnel.
Material is transported into the tunnel.
The pipeline systems inside the underground passage.
The pipeline system inside the underground passage
The pipeline systems inside the underground passage.
The pipeline system inside the underground passage

Like us on Facebook or follow us on Twitter to get the latest news about Vietnam!

Tuoi Tre News

More

Read more

;

VIDEOS

‘Taste of Australia’ gala dinner held in Ho Chi Minh City after 2-year hiatus

Taste of Australia Gala Reception has returned to the Park Hyatt Hotel in Ho Chi Minh City's District 1 after a two-year hiatus due to the COVID-19 pandemic

Vietnamese woman gives unconditional love to hundreds of adopted children

Despite her own immense hardship, she has taken in and cared for hundreds of orphans over the past three decades.

Latest news