Many foreign direct investment enterprises in the Loc An – Binh Son Industrial Park, which is located near the construction site of the big-ticket Long Thanh International Airport project in Dong Nai Province, a neighbor of Ho Chi Minh City, have complained about dust resulting from the leveling of the site, saying that it has affected their products and workers’ health.
Representatives of over 200 FDI enterprises in Dong Nai on Friday attended a meeting with the provincial People’s Committee.
At the meeting, Doan Huong Giang, head of the administration and human resources division at Elite Long Thanh Co. Ltd., said “dust has caused a great impact on our products.”
“We expect the provincial authorities, departments, and agencies to come up with appropriate solutions to support Elite and other companies in preventing dust from affecting laborers’ health, product quality, and business activities,” Giang added.
Doan Huong Giang, head of the administration and human resources division at Elite Long Thanh Co. Ltd. in Dong Nai Province, southern Vietnam says dust from the construction site of the Long Thanh International Airport project has affected the company’s business activities. Photo: A Loc / Tuoi Tre |
Many other enterprises shared the view.
Earlier, thousands of houses and a section of the Ho Chi Minh City-Long Thanh-Dau Giay Expressway near the Long Thanh International Airport project were also reported to be covered with dust from the construction site.
Dust from the construction site of the Long Thanh International Airport project blankets adjacent residential areas. Photo: A Loc / Tuoi Tre |
Do Tat Binh, deputy general director of the Airports Corporation of Vietnam (ACV), the investor of the mammoth airport project, on Friday told Tuoi Tre (Youth) newspaper that the corporation had asked contractors to enhance the spray of water at the construction site to limit dust.
The ACV will next week dispatch fire trucks to the site to spray water, Binh said, adding that the corporation will join forces with the local authorities to support local residents in cushioning the impact of dust.
The construction site is large and the leveling workload is huge amid the windy and dry season.
Fifty vehicles spraying water every day at the construction site is just a temporary solution and can reduce part of the dust.
“The leveling is expected to be completed by the end of May, when the rainy season will come, and the volume of dust will reduce,” Binh said.
According to the ACV, 2,630 workers along with 1,860 pieces of machinery are working to build the foundation of the airport project.
The airport project, which requires an estimated investment of VND336.63 trillion (US$14.2 billion) and is located some 40 kilometers from Ho Chi Minh City, will cover around 5,000 hectares of land and was designed to have an annual capacity of 100 million passengers and five million tons of cargo.
Once in place, it will be the largest airport in the nation.
At the conference, Nguyen Thi Kim Dung, a representative of Terumo BCT Co. Ltd. in the Long Duc Industrial Park in Long Thanh District, Dong Nai Province, also complained about the deterioration of a road connecting National Highway 51 and the industrial park.
This is a key road on which most workers of the enterprises in the area have to travel every day. However, it has been deteriorated for a long time.
The four-kilometer road has many potholes, posing a high risk of traffic accidents for road users, especially at night.
Some enterprises reported the issue to district- and province-level agencies in 2020. However, the road was repaired without care and it remains in bad conditions.
Representatives of FDI firms also mentioned the insecurity and disorder and power cuts without advance notice.
Chairman of the Dong Nai People’s Committee Cao Tien Dung said the province took responsibility for accompanying enterprises to overcome difficulties.
Leaders of the Dong Nai authorities give investment certificates to FDI enterprises. Photo: A Loc / Tuoi Tre |
After the conference, the director of the provincial Department of Planning and Investment must review enterprises’ complaints and report them to the provincial authorities to work out appropriate solutions, Dung said.
Regarding the road leading to the Long Duc Industrial Park, Dung asked Long Thanh District to quickly upgrade it.
The provincial Department of Planning and Investment and the Department of Transport were assigned to ensure traffic safety for workers traveling on the road.
The Dong Nai chairman also requested the relevant agencies to review and promptly handle foreigners’ temporary residence registration and immigration applications.
Departments and agencies must review the procedure handling to meet enterprises’ demands and provide the greatest possible support for them.