​Ho Chi Minh City to restart long-delayed repair work for Nguyen Huu Canh St

Saturday, September 23, 2017, 15:20 GMT+7

Repairs for the street notorious for its frequently getting flooded were planned in 2009 but work had never started

Ho Chi Minh City officials are planning to restart a project to repair the heavily sunken and frequently flooded Nguyen Huu Canh Street in District 1, eight years after the previous plan stalled due to budget.

The construction of the 3.7 km Nguyen Huu Canh Street, connecting District 1 and Binh Thanh District, began in 1997 and was completed in 2002.

However, not long after opening to traffic, various sections of the street have suffered submergence, resulting in flooding and heavy congestion under heavy rains for the past 15 years.

In 2009, the municipal administration tasked the local Ho Chi Minh City-based Construction Corporation No. 1 JSC with implementing repairs for the street that runs along the Saigon River.

The construction firm then proposed three different solutions for the work, whose budgets range from VND126.4 billion (US$5.56 million) to VND327.6 billion ($14.4 million), all of which were however beyond the affordability of the city’s budget at the time.

With such budget shortage, no major repair works have ever been carried out since 2009, leaving the road’s conditions worse year after year, with some sections sunken over one meter.

Consequently, the infamous street would easily become flooded whenever there are heavy rains or high tides, seriously affecting traffic and the lives of local residents.

At the beginning of 2017, to resolve the flooding problem, a centrifugal pumping system was installed on the street to pump out water when needed. However, the solution is only temporary and not sufficiently effective.

According to the municipal Department of Transport, local realty developer Vingroup has proposed to provide the city with capital without interest for three years to repair the road.

The reparation proposed by Vingroup will be done under the 'turnkey' scheme, in which the contract is solely carried out by the contractor from start to finish.

When the project is complete, it will be transferred to the city and ready to use.

If accepting the proposal by Vingroup, the Ho Chi Minh City administration will be responsible for allocating the given budget for this project.

TUOI TRE NEWS

More

Read more

The malling of Vietnam

I found myself wondering whether Vietnam’s malls would, in time, mimic America’s mall culture – the teenage human “mall rats” and the conspicuously “Valley Girls” that sprouted in the 1980s

6 years ago
;

Photos

VIDEOS

Experience summer sand-boarding in Mui Ne

Sand-boarding, a popular activity amongst local children in the coastal tourism town of Mui Ne in south-central Vietnam, is attracting hundreds of tourists to the Red Sand Dunes

Young maple trees given better protection as Hanoi enters rainy season

The trees are currently growing well, with green leaves and healthy branches.

Hunting skinks for food in southern Vietnam

Skink meat is known to be soft, tasty, and highly nutritious.

Vietnamese-made app allows people to grow real veggies via smartphone

Nguyen Thi Duyen, a young engineer in Hanoi, developed the app and its related services to help busy people create their own veggie gardens.

Chinese tourists hit by Vietnamese over dine and dash

Four Chinese were reportedly injured, with one having a broken arm.

Latest news