JavaScript is off. Please enable to view full site.

After 2 decades of construction, Ho Chi Minh City bridge to be opened to traffic next week

After 2 decades of construction, Ho Chi Minh City bridge to be opened to traffic next week

Tuesday, August 29, 2023, 20:36 GMT+7
After 2 decades of construction, Ho Chi Minh City bridge to be opened to traffic next week
A view of the new Long Kieng Bridge spanning the Phuoc Kieng River and connecting Phuoc Kien and Nhon Duc Communes in Nha Be District, Ho Chi Minh City. The new bridge is next to the deteriorated Long Kieng Bridge.

Ho Chi Minh City expects to put the Long Kieng Bridge project in its outlying district of Nha Be into use from Wednesday next week, 22 years after the project was formulated.

The municipal People’s Committee approved the project in 2001.

The 318-meter-long bridge project with two approaching roads measuring 661 meters in length required an estimated investment of VND589 billion (US$24.3 million), sourced from the city’s budget.

Its investor is the Transportation Works Construction Investment Project Management Authority of Ho Chi Minh City.

Workers complete auxiliary items, such as manhole covers, sidewalks, and median strips. Main items of the bridge have been completed.

Workers complete auxiliary items, such as manhole covers, sidewalks, and median strips. The main items of the bridge have been completed.

By 2007, just some households had handed over their land lots to make room for the project.

Work on the project did not start until August 2018. It was scheduled for completion at the end of November 2019.

However, site clearance bottlenecks slowed down the progress.

Until September last year, the People’s Committee of Nha Be District had not handed over the entire cleared site for the project.

The Ho Chi Minh City People’s Committee approved the new Long Kieng Bridge project in 2001. The 318-meter-long bridge project with two approaching roads measuring 661 meters in length requires an estimated investment of VND589 billion (US$24.3 million).

The Ho Chi Minh City People’s Committee approved the new Long Kieng Bridge project in 2001. The 318-meter-long bridge project with two approaching roads measuring 661 meters in length required an estimated investment of VND589 billion.

The new bridge will help revitalize the area and facilitate travel. Many local residents are excited as they will no longer have to pass over the deteriorated Long Kieng Bridge.

The new bridge will help revitalize the area and facilitate travel. Many local residents are excited as they will no longer have to pass over the deteriorated Long Kieng Bridge.

In 2018, the current Long Kieng Bridge collapsed when a truck carrying rocks was running on the bridge, sending the truck and many motorbikes to the river. It takes the local authorities 10 days to deal with the incident.

In 2018, the Long Kieng Bridge collapsed when a truck carrying rocks was running on it, sending the truck and many motorbikes down to the river. It took local authorities 10 days to deal with the incident.

The opening of the new Long Kieng Bridge is a dream of residents 22 years after it began construction.

The opening of the new Long Kieng Bridge has been a dream of residents during the past 22 years.

A road leading to the bridge in Nhon Duc Commune has been expanded.

A road leading to the bridge in Nhon Duc Commune, Nha Be District, Ho Chi Minh City has been expanded.

Contractors complete technical items of the bridge and approach roads.

Contractors complete technical items of the bridge and approach roads.

Workers plant trees under the bridge to prevent littering. In April 2023, vice chairman of the Ho Chi Minh City People’s Committee Bui Xuan Cuong required completing the bridge on June 30 and approach roads on July 30 at the latest. Other items should be completed later to put the project into service by the National Day (September 2) holiday.

Workers plant trees under the bridge to prevent littering. In April 2023, vice-chairman of the Ho Chi Minh City People’s Committee Bui Xuan Cuong required completing the bridge on June 30 and the approach roads on July 30 at the latest. Other items should be completed later to put the project into service by the National Day (September 2) holiday.

Like us on Facebook or  follow us on Twitter to get the latest news about Vietnam!

Thanh Ha - Chau Tuan - Le Phan / Tuoi Tre News

More

Read more

;

Photos

VIDEOS

‘Taste of Australia’ gala dinner held in Ho Chi Minh City after 2-year hiatus

Taste of Australia Gala Reception has returned to the Park Hyatt Hotel in Ho Chi Minh City's District 1 after a two-year hiatus due to the COVID-19 pandemic

Vietnamese woman gives unconditional love to hundreds of adopted children

Despite her own immense hardship, she has taken in and cared for hundreds of orphans over the past three decades.

Vietnam’s Mekong Delta celebrates spring with ‘hat boi’ performances

The art form is so popular that it attracts people from all ages in the Mekong Delta

Latest news